Material Consumption
Material Consumption functionality allows you to have multiple consumption
Stock Entry
against a Work Order. To enable this, go to Manufacturing > Manufacturing Settings.
Once enabled, a
Material Consumption
button will be available in Work Order once started.
When button is clicked, it will do the following:
-
It will create Stock Entry with purpose
Material Consumption for Manufacture
.
-
If the "Backflush Raw Materials Based On" in the Manufacturing Settings is set to
BOM
, if will propose to consume all required qty for manufacture. -
If the "Backflush Raw Materials Based On" in the Manufacturing Settings is set to
Material Transferred for Manufacture
, if will propose to consume all transferred qty for manufacture. -
Once submitted, it will update
Consumed Qty
column in the Work Order.
- In succeeding Material Consumption, it will suggest unconsumed qty.
- Once "Finish" button is clicked in Work Order, it will take into account consumed qty.
Validations
- If "Allow Multiple Material Consumption" is not set in Manufacturing Settings but "Material Consumption for Manufacture" is use in Stock Entry.
- Cannot cancel "Material Consumption for Manufacture" for completed Work Order.